The summer’s Rumson-Sea Bright Bridge replacement construction is on a status quo schedule again. Work is scheduled for the usual 7 a.m. to 3:30 p.m. through Friday, weather permitting. Specific construction activities scheduled for the week are listed below the travel advisory information.

Activity on and around the Shrewsbury River waterway surrounding the bridge …
- Normal bridge operations are expected at all times.
- The United States Coast Guard (USCG) has jurisdiction over the navigational channel. USCG may grant permission for partial closures of the channel and/or for temporary deviation from normal drawbridge operations. Monmouth County must comply with instructions from USCG.
On the roadways and sidewalk surrounding and on the bridge …
- There will be potential traffic pattern changes and possible travel delays on both sides of the bridge.
- All roadway and sidewalk travelers should be aware of construction and delivery vehicles entering and exiting the work areas on both sides of Rumson Road in Rumson and on the southbound side of Ocean Avenue in Sea Bright.
- The south side (eastbound) sidewalk of the bridge is closed.
Scheduled Construction Activities
Rumson
- Install permanent railing — west approach
- Install railing — fender access platform
- Install machinery guards
- Install trunnion access platform
- Install permanent engine exhaust
- Paint machinery
- Epoxy paint floors — control & gatekeeper house
- Paint stairs & railing — control & gatekeeper house
- Paint Doors — control & gatekeeper house
Sea Bright
- Controls work to bring leaf online
- Grounding and bonding of trunnion
- Commissioning & testing with WSP
- Operator training
- Fix/Repair — span position indicator shaft
- Install roller shead pockets
- Install drop ceiling
- Install marine radio
- Install lights — street level
- Install work desk, chair & locker
- Install anti-climb mesh
- Repair cracks in approach span deck
- Install tide clearance gauge lights (south fender)
- Install machinery guards
- Install trunnion access platform
- Install permanent engine exhaust
- Paint machinery
- Epoxy paint floors — control & gatekeeper house
- Paint stairs & railing — control & gatekeeper house
- Paint doors — control & gatekeeper house